Back to Top
Esterhazy K1 Mine Site

Esterhazy Transition Timing Update

June 4, 2021

This morning we announced that our Esterhazy transition timeline is shifting due to brine inflow conditions underground at K1 and K2. 

Recently, inflow volumes have risen faster than our models predicted. Given the current conditions, we are immediately suspending underground mining at K1 and K2, altering our timeline by nine months and impacting approximately 1 million tonnes of production from Esterhazy in 2021. We now expect to eliminate brine management expenses after July 2021.

To offset some of the production and take advantage of strong 2022 potash markets, we are actively pursuing production options at our Colonsay facility.

Mosaic has been managing inflows at Esterhazy since 1985 and accelerated the development of the K3 shafts to offset the impact of the final closure of the K1 and K2 shafts. For the last decade, we’ve run scenarios that relate to the early closure of these shafts. As a result of that planning, we expect to end up in a stronger position than ever in 2022.

More information is available here.

 

Shifting our Focus to the Future of Esterhazy

Shifting our Focus to the Future of Esterhazy

July 28, 2021

In early June, the Esterhazy transition timeline shifted due to brine inflow conditions underground at K1 and K2.ΓÇ»We immediately suspended underground mining at K1 and K2 and began actively pursuing production options at ourΓÇ»Colonsay facility. Plans are now underway to resume production there this summer.  

We’ve also shifted our focus to the future of Esterhazy – K3. When the project is complete in early 2022, our Esterhazy operation will be the largest, most competitive underground potash mine in the world.  

K3 has twin shafts that sink more than 3,000 feet – each covered by headframes that rise more than 300 feet above ground. The North shaft is used to move ore to the surface and transport people and equipment. The South shaft headframe, which houses a production hoist that will be used solely to transport potash, is expected to be substantially complete in October. Watch this video to learn more about the sinking of our K3 shafts.  


Ramping Up for Production at K3’s Second Shaft 
Consistent tons continue to come from K3’s completed North shaft, which provides ore supply to the K1 and K2 mills at an average rate of 30,000 tons per day. A new hoist record of 37,277 tons was set on July 11.  

K3’s South shaft headframe will be ready for full production in early 2022. Construction of the shaft’s 300-foot-tall headframe is now more than 90 percent complete. All six massive, 2,000-tonne steel floors on the headframe have been installed – each assembled at ground level before being raised into their final position using a hydraulic pumping system. The majority ofΓÇ»the utilities,ΓÇ»hoist cooling piping and electrical cabling have also been installed, with final piping connections, electrical terminations and testing expected to be completed by August.  


The South shaft headframe’s Koepe hoist will be used to transport rich potash ore from underground to the surface. From there, the ore will be carried on an overland conveyance system to the K1 and K2 mills.   

TheΓÇ»KoepeΓÇ»hoist, motorsΓÇ»and large ropeΓÇ»drum in the headframe are installedΓÇ»and being fitted with a braking system, electrical/instrumentation equipment and other ancillary equipment.ΓÇ»Hoisting equipment will be energized later this month to perform initial rotation of the hoist motors without ropes, with rope-up and installation of the large 60-ton skips to begin in September with commissioning to follow.  


K3’s south coarse ore bin shuttle conveyors will be used to transport ore from the large storage bin to the surge bin and loading pockets to fill the skip conveyances that are hoisted to surface.ΓÇ» 

Progress continues underground as well. Construction of the massive 6,000-ton-capacity south coarse ore bin was complete in June, and initial equipment commissioning on the bin and related conveyors is now underway.  

Automating K3’s Fleet of Mining Machines  
Seven four-rotor miners are currently in production at K3. Two additional miners will be added to the fleet later this year, with a total of 10 expected to be in operation by March 2022. These machines mine three “passes” – the first pass to set the direction and forge a new path through rock, then second and third passes to mine ore.    

Successful trialsΓÇ»ofΓÇ»“first pass” automation have been completed with two machines, and the entire fleet is expected to be operating autonomously for all three passes in fully developed production areas in early 2022. Running these machines with minimal human intervention reduces risk for our employees and eliminates downtime, as they can safely operate 24/7.ΓÇ» 

Workforce Plan in Place to Support our New Transition TimelineΓÇ»ΓÇ» 
Since the announced closure of K1 and K2 underground on June 4, our Esterhazy management and union executivesΓÇ»have worked together on a workforceΓÇ»plan to support the new transition timeline. Within two weeks, more than 200 hourly employees received orientation training and moved into temporary positions with the K1 and K2 mills and K3 underground operations.  

“We would like to thank everyone for their patience during this process,” said Dustin Maksymchuk, General Manager. “Through the hard work of our Esterhazy team and collaboration with our union executives, we have been able to maintain our full workforce without impacting employees and minimal downtime. We also remain vigilant in our commitment to safety – providing training, resources and other support to our employees as they transition into new roles.”   

ΓÇ» 

Mobile Technology_Esterhazy

NextGEN: Our Innovation Journey: Enabling Employees Through Deployment of Mobile Technology  

August 11, 2021

Image: Tony Sparvier, Sr. Engineer, saves electrical drawings and wiring diagrams for the automated hardware installer to his iPad for easy reference when working underground at Esterhazy’s K3.  

Mobile technology is being used across our North America Business – in big and small ways – to operate safely, responsibly and create the greatest possible value for Mosaic and our team. Getting technology into the hands of our employees provides them with easy access to the real-time information they need to do their jobs. It also helps us connect across sites and geographies to plan work, collaborate and align efforts. 

When an operator noticed an odd noise coming from a gearbox, he used his iPhone to record and send a short video to the maintenance supervisor. The supervisor had a technician listening to it within 15 minutes to diagnose severity. Without an iPhone, this could have taken half a shift or longer – potentially delaying action needed to ensure the repair was done as safely, quickly and cost-effectively as possible.  

This is just one example of how mobile technology is being used across our North America Business – in big and small ways – to operate safely, responsibly and create the greatest possible value for Mosaic and our team. “Getting technology into the hands of our employees allows them to quickly connect with others and provides easy access to real-time information they need to do their jobs,” explains Colin Alberts, Mobile Deployment Lead. “We’re able to work together across sites and geographies to plan work, collaborate and align efforts – which are more important than ever as we move forward as an integrated North America Business.”  

Our Esterhazy facility in Saskatchewan is leading the way with deployment of mobile technology – which will be crucial to enabling employees as we continue to focus on improving employee and customer experiences through digitization.  Learnings from work underway at Esterhazy and other Mosaic sites will help guide our efforts to expand use of mobile technology throughout our North America Business.  

Esterhazy: Pilot Launched in 2018  

Piloting and testing the deployment of mobile devices across the site began in 2018. The original driver was to enable electricians, mechanics and other craftspeople to receive, update and complete workorders from anywhere at the facility, but the team quickly began to see other areas where use of mobile devices could help drive value for Mosaic and the team. They also identified opportunities for improvement – one of which was making sure the appropriate support structure was in place to help users with technology set-up, maintenance and troubleshooting.  

They have also continued with deployment plans. Mobile devices are currently being used by nearly all maintenance personnel on the surface and are being deployed for use by production staff underground as well.  

“We’re always trying to make mobile technology better, more efficient and as helpful as possible for our employees – which will be an ongoing process,” says Colin.  

mosaic-in-canada

Readying K3ΓÇÖs South Shaft Headframe for Production

November 4, 2021

The future of Esterhazy is taking shape. Rich potash ore continues to be hoisted up K3’s completed north shaft at an average rate of more than 30,000 tons per day, and final work is underway to begin production at K3’s south shaft later this month.  

“Thanks to the dedication of our team and contract partners – the south shaft headframe will be safely completed approximately three months ahead of schedule,” explains Bernie Boutin, Director of Capital Projects – K3. “It was always a goal to accelerate completion of the south shaft headframe, mine ore storage bins and related conveyor systems, however the early closure of K1 and K2 made it that much more important.” 


Video: Two major “firsts” for our Esterhazy K3 project – potash ore being conveyed for the first time through the south coarse ore bin system on Oct. 5 and through the south surge bin system and up the south shaft headframe for the first time on Oct. 19.

Commissioning of the south shaft and mine ore handling system took place throughout October. First ore was safely and successfully conveyed through the massive 6,000-ton-capacity south coarse ore bin, and then conveyed through the south surge bin system up the south shaft headframe using the newly completed Koepe hoist and 60-ton skips. Ore from mining machines cutting in the south portion of K3 is conveyed to the south coarse ore bin. From here, it can be directed to either the south surge bin and hoisting system, or to the north surge bin and hoisting system.   

The focus now is on final preparations to begin production at the south shaft headframe this month – starting at 10,000 tons per day the first week then ramping up every week thereafter to achieve an additional 40,000 tons of hoisting capacity per day by December. By that time, a ninth four-rotor mining machine is also expected to be in production at K3 – with two additional mining machines expected to be in production at K3 by June 2022.  

Mining machines that are cutting in a production panel make three passes – the first pass to set the direction and forge a new path through rock, then second and third passes to mine ore. More than 21,000 feet (or 247,000 tons) have been cut by these machines utilizing first-pass automation since testing began in April, and the entire fleet is expected to be operating autonomously for all three passes in fully developed production areas in early 2022. Running these machines with minimal human intervention reduces risk for our employees and eliminates downtime, as they can safely operator 24/7.  

Esterhazy’s K3 has twin shafts that sink more than 3,000 feet – each covered by headframes that rise more than 300 feet above ground. The north shaft (on right) is used to move ore to the surface and transport people and equipment. The south shaft (on left) will be used solely to move ore to the surface. 


Esterhazy’s K3 has twin shafts that sink more than 3,000 feet – each covered by headframes that rise more than 300 feet above ground. The north shaft (on right) is used to move ore to the surface and transport people and equipment. The south shaft (on left) will be used solely to move ore to the surface. 



Video: Time-lapse video to see construction of the Koepe hoist in K3’s south shaft headframe.

Esterhazy K3: The Future is Here

Esterhazy K3: The Future is Here  

December 20, 2021

As of December 8, Esterhazy K3’s newly completed south shaft headframe is operating at full hoisting capacity. Production officially began November 8 following successful commissioning of the headframe and ore handling system in October.  

“Thanks to the dedication of our team and contract partners – the south shaft headframe was safely completed approximately three months ahead of schedule,” explains Bernie Boutin, Director of Capital Projects – K3. “It was always a goal to accelerate completion of the south shaft headframe, mine ore storage bins and related conveyor systems, however the early closure of K1 and K2 made it that much more important.”ΓÇ»  

Ramping Up K3’s Hoisting Capacity & Production
As planned, hoisting capacity of the south shaft headframe started at 10,000 tons per day and is increasing to 40,000 tons per day in December. Combined with the north shaft headframe, which has been in operation since 2018, this will bring K3’s hoisting capacity to more than 80,000 tons per day.  

 

Esterhazy K3's south shaft headframe officially began production in early November. It is used solely to move potash ore to the surface. K3's north shaft headframe - which has been in operation since 2019 - is used to move potash ore to the surface and transport people and equipment. 


Having the new south headframe and underground ore handling system in production removes current ore hoisting constraints and ensures capacity for additional ore supply as future mining machines are assembled and put into production.

Production at K3 is also ramping up with the addition of ore from the south shaft – reaching a new daily record of more than 43,000 tons by mid-November. Total tons will continue to increase with the recent addition of a ninth four-rotor mining machine and two more mining machines by June 2022. ΓÇ» 

“With both shafts now operational, our focus remains on increasing tons to fully leverage K3’s hoisting capacity,” explains Bradley Danylko, Sr. Mine Manager. “We’ll do that by continuing to grow our fleet of mining machines and use technology to find new ways to safely, efficiently make the quality products our customers depend on.” ΓÇ» 

Delivering on our Commitment to Safety 
"The K3 project required in excess of 12.5 million person-hours to execute the work, and there were up to 500 persons on site per day during peak construction periods. As the K3 project commences, we're proud to report that there were ZERO reportable injuries within Capital teams over the last 12 months,"  said Bernie Boutin, Director of Capital Projects – K3. "Mosaic is truly grateful for all the hard work and dedication of Capital and Operations team members, Hatch and Wood PLC, and all contractor groups that helped build K3. We're proud of the future that has been built for Mosaic, for our employees and for the communities we live in."


Growing K3’s Fleet of Automated Mining Machines 

A ninth four-rotor mining machine left the shop in November and is now in production at K3.  

Production at K3 is also ramping up with ore from the south shaft and the recent addition of a ninth four-rotor mining machine. Two more mining machines are expected to be in production by June 2022.  

“Safely and efficiently commissioning these automated mining machines requires teamwork—especially between our assembly, maintenance, production and automation teams,” says David Steiger, Sr. Mine Manager. “Each one is assembled in the shop then trammed to mining areas to begin production.”  

The machines make three passes to mine an area. On the first pass, they set the direction and forge a new path through rock while another automated machine follows behind them installing hardware to build a conveyer belt. During the second and third passes, the machines follow the path of the conveyer belt to mine ore—first on one side of the belt, then the other.  

Four of the nine mining machines currently in K3’s fleet are capable of operating autonomously in all three passes, and all nine are expected to be operating autonomously for all three passes in fully developed production areas in early 2022. Running these machines with minimal human intervention reduces risk for our employees and eliminates downtime, as they can safely operate 24/7. ΓÇ»  

Integrated Operations: Gaining Momentum through Collaboration  

Esterhazy K3’s Integrated Operations Center (IOC) is now complete – and we’re continuing to gain momentum on integrating operations across our Esterhazy site by collaborating with the Florida mining and concentrates teams, who are also integrating operations. 

“The current physical build in place is the IOC for K3—which manages the underground, hoists and ore flow to the mills,” explains Kyle Douglas, Engineer Lead. “The next step is incorporating operation of the K1 and K2 mills.”  

Ultrasonic sensors are now in place for the new advanced underground conveyor control system being developed to reduce conveyor downtime and optimize miner productivity. The system coordinates the automated mining machines with the underground storage bins to maintain steady-state ore flow across the conveyor network. It allows panel miners to maximize their production rate without loading belts past their design limits. The bins that they ultimately bump into will be kept full, but without overfilling—which should lead to more continuous operation.  

Another big step forward—new consoles have been installed that give us the ability to change operating screens at the touch of a single button on the smart keyboard. They provide rapid access to emergency and other priority screens, which can be integrated to allow access by the Emergency Operations Center during an emergency event.  

K3 Transition Workforce Plan: A Look Back  
When the K3 Transition workforce plan was first developed five years ago, it predicted we could reduce our headcount by more than 200 employees if we managed our natural attrition carefully. To do this, we partnered with our local Union and developed the “K3 Transition – Hourly Workforce Plan” Letter of Understanding (LOU), which acted as our key document on how employees would move into new or changed roles as we closed our K1, K2 and Inflow operations and moved over to K3. 

When K1, K2 and Inflow operations ended nine months earlier than projected, more 200 hourly employees temporarily transferred to new roles in under 10 days. A record-number of hourly roles—158 in total—were posted at one time to provide many options for employees to bid.ΓÇ» 

Our workforce plan was successful because Mosaic and the Union worked continuously throughout the transition to find the best solutions and opportunities for our employees.  

“Creating a workforce plan that allowed us to flex during our K3 Transition was very complex,” said Braden Domres, HR Manager - Esterhazy. “The success of this plan came from the strong partnership between our local Union Executive and our Management team and I would like to thank this group for creating a strategy that supported our employees as they shifted into new roles within our operations."

k3-workers

Esterhazy K3: A Quick Look Back

April 14, 2022

After more than 12 years, close to 13 million workhours and billions of dollars in capital investment – Esterhazy K3 is nearly complete. Take a quick look back at how the vision for K3 became a reality.

In 2009, Mosaic embarked on our Esterhazy K3 project – a $3 billion-dollar investment in the long-term sustainability of our operations, Esterhazy and the vision we have for the future of our North America Business. More than 12 years and almost 13 million workhours later, the K3 project is nearly complete. The project timeline was accelerated to help offset impacts of the final closure of the K1 and K2 shafts in June 2021.

Esterhazy’s K3 is Saskatchewan’s first new underground potash mine in over a half-century. Potash ore mined 3,350 feet below the surface is hoisted up two shafts – North and South – using equipment in over 330-foot-tall headframes that can be seen spanning the horizon from miles away. Overland conveyor systems then carry K3 ore to the existing K1 and K2 mills for processing.

As of the end of March 2022, there are nine mining machines cutting underground at K3 that can provide up to 50,000 ore tons per day – with a new daily record of 62,000 tons being set on January 23. Another mining machine is nearing production, and three more mining machines and more underground conveyors will be added over the next couple of years.

Read more about Esterhazy K3 here.ΓÇ»